The primary audit objective was to determine whether measures were in place to monitor and, where appropriate, reduce administrative lead time for awarding consumable and repairable spare parts procurement contracts. However, this report discusses only consumable items. Repairable items are not discussed in tins report because repairable items are procured differently than consumable items, and because the Air Force acquisition process for repairable items is different ...
Introduction. The audit was directed by Public Law 102-190, "National Defense Authorization Act for Fiscal Years 1992 and 1993," December 5, 1991. The Public Law states that the Secretary of Defense shall ensure that the amount of the authorization requested by DoD for each military construction project associated with base realignment and closure actions does not exceed the original estimated cost provided to the Base Closure and ...